Road Work / Closures
Road Work

ROAD CONSTRUCTION - SUMMER SCHEDULE

Road Work

The Road & Bridge Department will be working on various County roads starting the week of May 18th (weather permitting). Here is the remaining summer schedule:

Gunn Creek Culvert Replacement August 17th - Sept Sept 21, 2015.  The project will maintain one lane of traffic at all times. However, there will be times where traffic will be stopped intermittently for certain construction activities. Please be prepared for traffic delays.

Overlay July 27 - October 9th

Overlay RCR 27 US 131 @Oak Creek (MM 0) to RCR 31 Middle Creek ( MM6.7)
Overlay RCR 35 RCR 41 to RCR 14
Overlay RCR 53 Seneca Haul Rd ( MM5.9) to Hayden City Limits ( MM 12)
Overlay RCR 129 State Park Office ( MM 25) to End of Pavement ( MM 29.8)


Striping Phase 2  (paved and chip sealed roads) From Aug 15 To September 25th



Completed Projects:
Dust abatement ( Mag-Chloride) - From May 18th to June 12th - Done!

Patch - From June 23rd to July 15th - Done!

RCR 14 Reconstruction - North of Stagecoach State Park - July 13th to August 20th.

  • July 20th - August 3rd: Complete Road Closure between Hibbert Lane and Henderson Park Rd  - Done!
  • August 4th  - 11th: CR 14 is open with long delays possible from 7 am to 7 pm during final work and paving.Detour via 131 is recommended.
  • August 11th to the 20th there may be intermittent flagging and minor delays as the final project work is completed. 

Middle Creek Bridge RCR 27- Bridge Replacement - July 13th to August 10th. CR 27 Closed at Old County Road 31 ( between CR 29 and CR 33) to replace the bridge. Use detour via CR 29. Done!

Chip Seal - From July 20 - August 10th - Done!

Project Road Section
Chip RCR 14 Hudspeth, Highway 131 (MM11.2) to RCR 35 (MM 13)
Chip RCR 27 Phase 4/ RCR 33 (MM 9.0) to RCR 37 ( MM 13.5)
Chip RCR 27 Phase 1/ RCR 37 ( MM 13.5) to end Phase I Point 1.76 miles North ( MM 15)
Chip RCR 27 Phase 2 / end Phase 1 ( MM 15) to start Phase 3 ( MM 18)
Chip RCR 27 Phase 3/ End Phase 2 ( MM 18) to RCR 27A Roundabout ( MM 21)
Chip RCR 27 Phase 5/ RCR 27A Roundabout ( MM 21) to US 40 ( MM 24)
Chip RCR 42 Four Mile/ Silver Spur Street(M.M.3.3) to US 40 (MM 4.35)
Chip RCR 42 Four Mile/ Marabou Entrance ( MM3.3) to Silver Spur Street ( MM 1.5)
Chip RCR 53 RCR 53 from city limits (MM13.3) to (MM12) ( past Haul road.)
Chip RCR 78 Fredrickson's Hill/ gravel to gravel. (MM1.5 to MM 2.6)
Chip Radiator Road

For additional information or updates, please contact the Road & Bridge Department at (970) 879-0831.
(updated 8/26/15)


Road Closures
Roads Open for summer travel. Some roads may be impassible when wet. Some roads are native surface and 4 wheel drive is recommended. Know your route and plan travel accordingly. (updated 6/23/15)